The City of Stonnington is in an election period and operating under caretaker conventions until 6pm on 26 October.
Council election
In November 2021, work will be undertaken to widen the section of the Main Yarra Trail shared path, between Verdant Avenue and the Winifred Crescent Reserve in South Yarra.
These works will bring this section of the shared path up to the same standard as most other sections of Yarra River shared paths in Stonnington. It will be widened and resurfaced with asphalt, to the match the paths at each end.
During the works the path will remain open to cyclists and pedestrians.
We recognise works of this nature will cause some temporary inconvenience and we thank you in advance for your patience and understanding.
Relocate kerb
Widen path
New asphalt surface
November 2021 to January 2022
Travis Jenkins
M: 0419 835 646
E: tjenkins@stonnington.vic.gov.au
Blue Peak Constructions
Felipe Rodriguez
M: 0411 074 143
Download Yarra Main Trail design drawings(PDF, 6MB)