Once you receive your Vehicle Crossing Permit, we inspect the site before and after the concrete pour to check it meets the correct standards.
The property owner is responsible for all works undertaken by contractors.
About the pre-pour inspection
We inspect on the day of the concrete pour.
During the inspection, we check the preparation and discuss how to complete the crossing to the correct standard.
How to book
You or your representative must set aside a weekday morning and be on site at the arranged inspection time.
At least 2 business days before the concrete pour, call to 0417 318 736 to arrange an inspection time.
After the works
When you’ve completed your works, let us know by calling at 0417 318 736. Please let us know within 14 days of completing the work.
We’ll conduct a final inspection after the concrete pour to ensure the vehicle crossing meets the correct standards.