Thomas Street South, Windsor - Road Reconstruction
In line with our commitment to maintaining community infrastructure assets to the highest standard and as part of the Local Roads and Community Infrastructure Program, Thomas Street South in Windsor is being reconstructed.
Works are starting to in mid-September 2021 and are expected to be completed by the end of November 2021.
We recognise works of this nature may cause some inconvenience and we thank you in advance for your patience and understanding.
During the works, detours will be in place.
Project overview
Project status |
Complete |
Project type |
Road reconstruction |
Scope of works |
New underground drainage
New footpath
New kerb and channel
New concrete vehicle crossing (charcoal)
Asphalt resurfacing of road
Reinstatement works
|
Construction timeline |
Start date: late-September 2021
Completion date: mid-November 2021
|
Contacts |
Construction contractor
Panhold Constructions Pty Ltd
Jon Holda | 0412 434 320
City of Stonnington
Project Engineer
Connor Curtin | 03 8290 1302
E: ccurtin@stonnington.vic.gov.au
Project Manager
John Sherrard | 03 8290 3541
E: jsherrar@stonnington.vic.gov.au
Emergency (all hours) | 03 8280 1333
|