Prahran Aquatic refurbishment
Over several stages we will be refurbishing the popular Prahran Aquatic Centre. Open since 1963 and previously updated in the 90s, the pools and buildings are showing signs of wear and tear and need a refresh.
The first package of works was delivered in 2023, when the Centre was closed for a months long refurbishment of the 50-metre and toddler pools and surrounds, plus repairs and upgrades to the grandstand seating, changerooms and spa and sauna areas.
In 2025, the aged timber sundeck overlooking the 50-metre pool will be renewed with composite timber decking that will improve the quality, safety and durability of the deck while retaining the look and feel of timber.
The refurbishment works will bring the centre to a serviceable level for the mid-term, with a full redevelopment planned for later through the Princes Gardens masterplan implementation.
Completed works
Project type |
Sundeck refurbishment and associated repairs |
Project status |
Complete |
Construction timeline |
January to March 2025 |
Scope of works |
Remove existing timber decking
Install new composite timber decking
Repair adjacent timber steps
|
Project type |
Improvement / refurbishment works and repairs |
Project status |
Complete (Centre reopened 1 November 2023) |
Scope of works |
Repair and tile the outdoor 50m and toddler pools
Repair the outdoor area concourse
Repair tiles and update fixtures and fittings in the change rooms
Improvement works to the spa and sauna areas
Minor repairs to grandstand benches and outdoor seating
|