Motherwell Street Reconstruction

Signs of roadworks, triangle with man digging, witches hat, hard hat

About the project

The City of Stonnington is upgrading Motherwell Street in South Yarra between Hobson Street to Surrey Road.

The project will be completed in two stages, commencing at the Surrey Road end. Stage two works will commence at a date to be confirmed.

We recognise works of the nature will cause some inconvenience. Every effort will be made to keep disruption to a minimum and we thank you for your patience and understanding.

Latest news

April 2022

Resident Notification No. 1(PDF, 106KB)

October 2022

Due to unforeseen circumstances (contractor availability, inclement weather and latent conditions), there has been a delay in delivering this project. We apologise for any inconvenience, and we thank you for your patience and understanding.

Project overview

Project status COMPLETE
Project type Road reconstruction
Scope of works
  • Renew bluestone kerb and channel
  • Improve drainage
  • Renew asphalt footpath
  • Reconstruct Cromwell Road/Motherwell Street roundabout
  • Asphalt road resurfacing
Construction timeline

Start date: July 2022

Completion date: December 2022