Motherwell Street Reconstruction
About the project
The City of Stonnington is upgrading Motherwell Street in South Yarra between Hobson Street to Surrey Road.
The project will be completed in two stages, commencing at the Surrey Road end. Stage two works will commence at a date to be confirmed.
We recognise works of the nature will cause some inconvenience. Every effort will be made to keep disruption to a minimum and we thank you for your patience and understanding.
Latest news
April 2022
Resident Notification No. 1(PDF, 106KB)
October 2022
Due to unforeseen circumstances (contractor availability, inclement weather and latent conditions), there has been a delay in delivering this project. We apologise for any inconvenience, and we thank you for your patience and understanding.
Project overview
Project status |
COMPLETE |
Project type |
Road reconstruction |
Scope of works |
- Renew bluestone kerb and channel
- Improve drainage
- Renew asphalt footpath
- Reconstruct Cromwell Road/Motherwell Street roundabout
- Asphalt road resurfacing
|
Construction timeline |
Start date: July 2022
Completion date: December 2022
|
Map of work zone
Motherwell Street - Hobson Street to Surrey Road