Meryl Street - Road Reconstruction

Signs of roadworks, triangle with man digging, witches hat, hard hat

In November 2021, we will be completing road reconstruction works in Meryl Street, Armadale - between Hume and Union streets.

These works will deliver:

  • new concrete vehicle crossings
  • new asphalt footpaths
  • new concrete kerb and bluestone channel
  • new underground drainage
  • new asphalt road pavement.

The new road surface level will be adjusted to improve driveway access and kerbside parking.

We recognise work of this nature may cause some inconvenience and every effort will be made by the contractor and the city to keep this to a minimum.

We thank you for your patience and understanding as we complete these important improvement works.

Project overview

Project status Complete
Project type Road reconstruction
Scope of works 

New concrete vehicle crossings

New asphalt footpaths

New concrete kerb and bluestone channel

New underground drainage

New asphalt road pavement.

Construction timeline 

Start date: early-November 2021

Completion date: April 2022

Hours of work 

7am to 5pm Monday to Friday

8am to 5pm Saturday