The City of Stonnington is upgrading the raised pedestrian crossing in Dunlop Street, Malvern East – at the crossing with the Gardiners Creek Trail.
The works are programmed to commence in May and will take approximately six weeks to complete.
During construction, detours will be in place around the Dunlop Street pedestrian crossing works zone. The detour will be signposted and traffic controllers in place to assist where required.
We recognise works of this nature will cause some inconvenience. Every effort will be made to keep disruption to a minimum and we thank you in advance for your patience and understanding.
Construct asphalt footpath with concrete edge restraints
Construct asphalt raised platform with access ramps
Reconstruct adjacent road pavement, kerb and channel
Advance bicycle detection loops and traffic signal works
Drainage works
May to July 2024
(works are ongoing)
May 2024 - Project update 1(PDF, 747KB)
17 July 2024 - Project update 2
All upgrade works are complete except for the relocation of one light pole.
Relocation of the pole has taken a little longer than anticipated, but we now expect this to happen in March or April.
Detours will be in place around the crossing point. Cyclists may need to dismount for their safety and that of other path users.