Cummins Grove road reconstruction

Signs of roadworks, triangle with man digging, witches hat, hard hat

In line with our commitment to managing and maintaining community infrastructure assets to the highest standard, Cummins Grove in Malvern has been listed for reconstruction.

Works are scheduled to commence in late-May 2021 and take around 12 weeks to complete.

We recognise works of nature may cause inconvenience and every effort will be made to keep disruption to a minimum. We thank you in advance for your patience and understanding.

During the works, detours will be in place.

Latest news

16 August 2021

Read Resident Notification(PDF, 699KB)

Project overview

Project status Complete
Project type Road reconstruction
Scope of works 

Reconstruct kerb and channel

Reconstruct footpath with concrete

Reconstruct road pavement with asphalt

Construction timeline 

Start date: late-May 2021

Completion date: mid-August 2021