Reconstruction of Charles Street from Commercial Road to Greville Street will be delivered over four stages:
Stage 1 | site set-out
Duration | one week (approx)
Stage 2 | Commercial Road to Thomas Place
Construct new underground drainage, kerb and channel, asphalt footpath and structural soils to allow for new tree planting within the street.
Duration | 10 weeks (approx)
Stage 3 | Thomas Place to Greville Street
Construct new underground drainage, kerb and channel, asphalt footpath and structural soils to allow for new tree planting within the street.
Duration | six weeks (approx)
Stage 4 | Asphalt pavement works and site decommissioning
Duration | 15 days (approx)
|